โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.16. Example:-II of CPI and SPIEasyโญ๐ก๐๐VU๐๏ธVU
According to 'Example 2 of CPI and SPI' in Module 05, with a Planned Value (PV) of 112, Actual Value (AV) of 216, and Earned Value (EV) of 40, what are the calculated CPI and SPI values, and what is the overall status of the project?
๐ป python Snippet
EV = 40
AV = 216
PV = 112
cpi = EV / AV # 0.185
spi = EV / PV # 0.357
A.CPI = 0.518, SPI = 1.928; Project is Under Budget and Ahead of Schedule.
B.CPI = 0.185, SPI = 0.357; Project is Over Budget and Behind Schedule.
C.CPI = 1.000, SPI = 1.000; Project is exactly On Budget and On Schedule.
D.CPI = 0.357, SPI = 0.185; Project is Under Budget and Behind Schedule.
Q33
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.15. Example:-I of CPI and SPIEasy๐๐VU๐๏ธVU
In the context of the April 20th project audit (Example 1), what do the single asterisk (*) and double asterisk () symbols next to the Actual Value (AV) and Completed Tasks Effort represent?
B.* represents the sum of actual effort planned to be completed by 20-April-2016; represents the sum of all tasks with Status = Completed by 20-April-2016.
C.* represents the number of developers allocated; represents the number of code lines completed.
D.* represents the total project budget; represents the client's approved invoice amount.
Q34
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.13. Earned Value Management (EVM)Mediumโญ๐ก๐๐VU๐๏ธVU
What is the primary nature and format of Earned Value Management (EVM) as described in Module 05 of the course handouts?
A.It is a financial accounting tool whose results are presented in tabular balance sheets.
B.It is a developer code-refactoring tool whose results are integrated into compilation logs.
C.It is a project management tool (not a financial tool) whose results are presented in a graphical format.
D.It is a software quality assurance unit testing engine that outputs text execution ratios.
Q35
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.14. CPI and SPIMedium๐โญ๐ก๐๐VU๐๏ธVU
How is the Cost Performance Index (CPI) mathematically defined under CMMI Module 05, and what is the project status if CPI > 1?
๐ป python Snippet
CPI = EV / AV
A.CPI = EV รท AV; indicates the project is under budget.
B.CPI = AV รท EV; indicates the project is over budget.
C.CPI = PV รท AV; indicates the project is as per the planned budget.
D.CPI = EV รท PV; indicates the project is ahead of schedule.
Q36
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.12. Audit of Each Phase of PM Process AreaMedium๐โญ๐ก๐๐VU๐๏ธVU
Comparing Project D and Project E in the Sample Project Audit Report, which additional compliant element allows Project E to achieve a 'Good' health rating instead of 'Satisfactory'?
A.A compliant and verified Demo Plan.
B.A compliant and formally documented Updated Plan ('Yes' instead of 'NA').
C.A compliant Scope management baseline.
D.An optimized and approved Budgeted Effort plan.
Q37
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.12. Audit of Each Phase of PM Process AreaEasy๐ก๐๐VU๐๏ธVU
Based on the Response Glossary in the Project Audit guidelines, how is the 'Very Good' rating defined?
A.Exceeded the expectation and acts as a role model for others.
B.Basic objectives met but there is room for improvement.
C.Exactly as per the expectations with zero minor defects.
D.Serious inability to comply with any of the established expectations.
Q38
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.15. Example:-I of CPI and SPIMediumโญ๐ก๐๐VU๐๏ธVU
According to 'Example 1 of CPI and SPI' in Module 05, with a Planned Value (PV) of 206, Actual Value (AV) of 358, and Earned Value (EV) of 230, what are the calculated CPI and SPI values, and how does the handout interpret the scheduling result despite a mathematical discrepancy?
A.CPI = 1.116, SPI = 0.642; interpreted as Under Budget and Behind Schedule.
B.CPI = 0.642, SPI = 1.116; mathematically the project is ahead of schedule (SPI > 1), but the handout text concludes the project is 'Behind Schedule' due to a documentation error.
C.CPI = 0.850, SPI = 0.950; interpreted as exactly on track and on budget.
D.CPI = 1.554, SPI = 0.895; interpreted as Under Budget and Ahead of Schedule.
Q39
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.14. CPI and SPIEasyโญ๐ก๐๐VU๐๏ธVU
What is the formula to calculate the Schedule Performance Index (SPI), and what does an SPI value of less than 1 (SPI
๐ป python Snippet
SPI = EV / PV
A.SPI = EV รท AV; indicates the project is under budget.
B.SPI = EV รท PV; indicates the project is behind schedule.
C.SPI = PV รท EV; indicates the project is ahead of schedule.
D.SPI = AV รท PV; indicates the project is on time.
Q40
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.13. Earned Value Management (EVM)Easy๐โญ๐ก๐๐VU๐๏ธVU
What is the core purpose of utilizing Earned Value Management (EVM) in a software project under CMMI Process Management?
A.To replace daily SCRUM standup meetings with automated milestone invoices.
B.To provide objective measures of cost and schedule performance and timely highlight issues for remedial action before it is too late to recover.
C.To automatically generate missing system test cases from functional use cases.
D.To eliminate the need for project plan baselines and support arbitrary development.