Ch 08: Project Scheduling and Network Diagrams

74 Questions74 MCQs0 Short Questions0 Long Questions
🎯 Exam Practice Papers
SEMESTER PASS

CS615 - Software Project Management Examination Practice

Timed practice exam simulation for CS615 - Software Project Management.

📘 VU MID TERM EXAMLectures 1 to 22
⏱️ 60 Mins

Mid Term Examination

Covers syllabus of Lectures 1 to 22 with 30 high-yield MCQs in a timed exam environment.

📝30 MCQs
⏱️60 Minutes
📗 VU FINAL TERM EXAMLectures 23 to 45
⏱️ 90 Mins

Final Term Examination

Comprehensive semester exam preparation with 45 MCQs covering Lectures 23 to 45 with complete course coverage.

📝45 MCQs
⏱️90 Minutes
Showing 21 – 30 of 74 Questions
Page 3 of 8
Q21
📝 Short Q📘 CS615📑 Lec 8🏷️ 08.3. Cost Estimation Models (COCOMO)Medium⭐💡📄🎓VU🏛️VU
What is the primary purpose of the basic COCOMO technique and when is it most appropriate to use it?
Q22
📝 Short Q📘 CS615📑 Lec 8🏷️ 08.3. Cost Estimation Models (COCOMO)Medium⭐📄🎓VU🏛️VU
What are the three steps involved in estimating project effort using the basic COCOMO technique?
Q23
📝 Short Q📘 CS615📑 Lec 8🏷️ 08.3. Cost Estimation Models (COCOMO)Medium⭐💡📄🎓VU🏛️VU
How does the project type influence the effort estimation in the Basic COCOMO model?
Q24
🧠 Long Problem📘 CS615📑 Lec 8🏷️ 08.2. Decomposition Techniques & Software SizingHard⭐💡📄🎓VU🏛️VU
Define the Source Lines of Code (SLOC) estimation technique. Discuss its main disadvantage regarding language dependency with an example comparing assembly and Visual Basic.
Q25
🧠 Long Problem📘 CS615📑 Lec 8🏷️ 08.2. Decomposition Techniques & Software SizingHard⭐💡📄🎓VU🏛️VU
Explain the advantages of using the Function Point (FP) estimation technique over the Source Lines of Code (SLOC) technique, particularly regarding language dependency and project model flexibility.
Q26
📝 Short Q📘 CS615📑 Lec 8🏷️ 08.2. Decomposition Techniques & Software SizingMedium⭐💡📄🎓VU🏛️VU
Explain why the Function Point (FP) technique is particularly effective for estimating projects that utilize Prototyping or Spiral lifecycle models.
Q27
❓ MCQ📘 CS615📑 Lec 8🏷️ 08.2. Decomposition Techniques & Software SizingMedium⭐💡📄🎓VU🏛️VU
Why is the Function Point (FP) estimation technique preferred over Source Lines of Code (SLOC) when software requirements are expected to change mid-project?
  1. A.Because SLOC is language-independent and adapts automatically to changes
  2. B.Because FP estimates are based on a subjective, holistic approach that is less likely to be invalidated by mid-project changes
  3. C.Because FP calculation requires a complete and final database schema before starting the project
  4. D.Because SLOC uses more complex mathematical formulas that require highly experienced developers to solve
Q28
🧠 Long Problem📘 CS615📑 Lec 8🏷️ 08.2. Decomposition Techniques & Software SizingHard⭐💡🌟📄🎓VU🏛️VU
Define the Delphi technique as an estimation technique, name the three distinct groups of people involved in its sessions, and explain its eight-step process.
Q29
❓ MCQ📘 CS615📑 Lec 8🏷️ 08.1. Estimation Concepts & Critical FactorsEasy⭐💡📄🎓VU🏛️VU
In software project management, which factor acts as the primary baseline from which a manager estimates the cost, effort, and duration of the project?
  1. A.The technical complexity of the code
  2. B.The size of the project
  3. C.The number of testing cycles
  4. D.The customer's target delivery date
Q30
📝 Short Q📘 CS615📑 Lec 8🏷️ 08.3. Cost Estimation Models (COCOMO)Medium⭐💡📄🎓VU🏛️VU
What is the Constructive Cost Model (COCOMO), and what are its three levels of implementation?