Ch 05: Project Planning & Software Development Plan (SDP)

41 Questions41 MCQs0 Short Questions0 Long Questions
๐ŸŽฏ Exam Practice Papers
SEMESTER PASS

CS615 - Software Project Management Examination Practice

Timed practice exam simulation for CS615 - Software Project Management.

๐Ÿ“˜ VU MID TERM EXAMLectures 1 to 22
โฑ๏ธ 60 Mins

Mid Term Examination

Covers syllabus of Lectures 1 to 22 with 30 high-yield MCQs in a timed exam environment.

๐Ÿ“30 MCQs
โฑ๏ธ60 Minutes
๐Ÿ“— VU FINAL TERM EXAMLectures 23 to 45
โฑ๏ธ 90 Mins

Final Term Examination

Comprehensive semester exam preparation with 45 MCQs covering Lectures 23 to 45 with complete course coverage.

๐Ÿ“45 MCQs
โฑ๏ธ90 Minutes
Showing 11 โ€“ 20 of 41 Questions
Page 2 of 5
Q11
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.3. Software Development Plan (SDP) StructureEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
________ is a project management technique used to integrate the project's scope, schedule, and resources and to measure and report project performance from initiation to closeout.
  1. A.Work Breakdown Structure (WBS)
  2. B.Earned Value Management (EVM)
  3. C.Critical Path Method (CPM)
  4. D.Function Point Analysis (FPA)
Q12
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.2. Planning Puzzle & Primary Planning StepsEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
In software project planning, ________ is defined as the process of progressively elaborating and documenting the project work (project scope) that produces the product of the project.
  1. A.Scope Planning
  2. B.Quality Planning
  3. C.Risk Planning
  4. D.Cost Budgeting
Q13
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.3. Software Development Plan (SDP) StructureEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
In project controlling and execution, ________ is defined as anything done to bring expected future project performance in line with the project plan.
  1. A.Preventive action
  2. B.Corrective action
  3. C.Defect tracking
  4. D.Scope creep
Q14
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.2. Planning Puzzle & Primary Planning StepsEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
________ is defined as the process of progressively elaborating and documenting the project work (project scope) that produces the product of the project.
  1. A.Scope planning
  2. B.Cost estimating
  3. C.Quality control
  4. D.Risk identification
Q15
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.4. Elements of SDP & Contractual AspectsEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
The primary ________ of the scope planning process are the written scope statement and the scope management plan, accompanied by supporting details.
  1. A.Inputs
  2. B.Tools and techniques
  3. C.Outputs
  4. D.Constraints
Q16
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.4. Elements of SDP & Contractual AspectsEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
In a Software Development Plan (SDP), the Technical Approach section describes how the new system is to be developed. All of the following are typically detailed in the Technical Approach EXCEPT:
  1. A.Technologies and architectural layers to be used
  2. B.Decisions on in-house development vs. external consultants
  3. C.Derivatives of existing systems or object models
  4. D.Detailed financial auditing and tax reporting procedures
Q17
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.3. Software Development Plan (SDP) StructureEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
In project plan execution, requests to expand or contract project scope, or to modify cost or schedule estimates, are examples of:
  1. A.Work results
  2. B.Change requests
  3. C.Baseline freezes
  4. D.Quality audits
Q18
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.2. Planning Puzzle & Primary Planning StepsEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
________ is the process of progressively elaborating and documenting the project work that produces the product of the project.
  1. A.Scope planning
  2. B.Cost budgeting
  3. C.Quality planning
  4. D.Risk response control
Q19
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.3. Software Development Plan (SDP) StructureEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
In software project management terminology, the acronym SDP stands for:
  1. A.Software Development Plan
  2. B.System Design Process
  3. C.Software Delivery Protocol
  4. D.Standard Developer Procedure
Q20
โ“ MCQ๐Ÿ“˜ CS615๐Ÿ“‘ Lec 5๐Ÿท๏ธ 05.1. Project Planning Objectives & DefinitionEasy๐Ÿ”โญ๐Ÿ“„๐ŸŽ“VU๐Ÿ›๏ธVU
Because computer software deteriorates over time due to ongoing changes, preventive maintenance is conducted, which is often referred to as:
  1. A.Software reengineering
  2. B.Corrective debugging
  3. C.Adaptive coding
  4. D.Regression testing