Risk and Change Management

Lecture 9: Risk and Change Management

106 Questions36 MCQs46 Short Questions24 Long Questions
Showing 3140 of 106 Questions
Page 4 of 11
Q31🧠 Long Problem📑 Lec 11HardHigh-Yield💡Conceptual🌟Starred
Discuss the roles of risk mitigation, risk monitoring, and contingency planning in software risk management. Explain how a project manager transitions from risk mitigation to contingency planning when a risk materializes, using high staff turnover as an example.
Q32❓ MCQ📑 Lec 11EasyHigh-Yield💡Conceptual
Which of the following is defined as a project tracking activity with the primary objective of assessing whether predicted risks do, in fact, occur?
  1. A.Risk Identification
  2. B.Risk Mitigation
  3. C.Risk Monitoring
  4. D.Risk Analysis
Q33📝 Short Q📑 Lec 11MediumHigh-Yield💡Conceptual🌟Starred
Differentiate between risk mitigation and risk monitoring, and describe the three initial objectives of risk monitoring.
Q34📝 Short Q📑 Lec 11HardHigh-Yield💡Conceptual
What is software safety and hazard analysis, and when should these SQA activities be conducted during software engineering?
Q35❓ MCQ📑 Lec 11MediumHigh-Yield💡Conceptual
Which of the following is a primary objective of software safety and hazard analysis, and when should these activities ideally be conducted?
  1. A.To identify and assess potential hazards early in the software engineering process so that design features can eliminate or control them.
  2. B.To perform exhaustive testing during the system implementation stage to locate coding syntax errors.
  3. C.To calculate source lines of code (SLOC) after the system has been fully delivered to the client.
  4. D.To manage the project budget and financial plans after the final deployment of the software.
Q36📝 Short Q📑 Lec 11MediumHigh-Yield💡Conceptual
Distinguish between development process risks and product-related risks in software project management, providing two examples for each category.
Q37❓ MCQ📑 Lec 11EasyHigh-Yield💡Conceptual
Which of the following is classified as a development process risk rather than a product-related risk?
  1. A.Complexity of the software product
  2. B.Incomplete and unclear requirements
  3. C.Disgruntled employees and developer errors
  4. D.Unclear project deliverables and objectives
Q38🧠 Long Problem📑 Lec 11HardHigh-Yield💡Conceptual
In the context of software engineering, describe Robert Charette's three conceptual underpinnings of risk and explain how each manifests in software projects.
Q39❓ MCQ📑 Lec 11EasyHigh-Yield💡Conceptual
Which of the following are the three conceptual underpinnings of risk identified by Robert Charette in the context of software engineering?
  1. A.Certainty, Stability, and Execution
  2. B.Future, Change, and Choice
  3. C.Past Performance, Code Size, and Developer Capability
  4. D.Planning, Organizing, and Controlling
Q40❓ MCQ📑 Lec 11EasyHigh-Yield💡Conceptual
In software engineering, Robert Charette defines risk through three conceptual underpinnings. Which of the following options correctly identifies these three conceptual underpinnings?
  1. A.Planning, Scheduling, and Budgeting
  2. B.Future, Change, and Choice
  3. C.Scope, Time, and Quality
  4. D.Avoidance, Monitoring, and Management